The work to replace the non-compliant stair and balustrade to the balcony area to the Milang Institute to meet current fire safety requirements was completed in April 2015. Work included:

  • Removal and replacement of existing non-compliant timber stair leading from the entrance foyer to the balcony
  • Supply and installation of a new steel balustrade behind the existing cast iron balustrade to the balcony
  • Removal and infilling of the existing upper level timber door and frame with masonry construction
  • Cutting back of existing timber bench seating to the balcony area to accommodate the new wider stair
  • Revised structural steel connection details and new concrete strip footing to adequately support the steel framework for the new stair
  • Painting of walls, existing doors and windows to the foyer area
  • Application of oil finish to the existing timber benches.

stairs

renovations

Milang Institute Building Renewal Works

Building renewal works to include replacement of guttering and downpipes and maintenance on external vents were complete in  October  2022.