Project updates are listed in order of township location below.
Ashbourne Stormwater Mitigation Project
Ashbourne residents have been significantly impacted by both locally generated overland stormwater flows and floodwaters from Bull Creek breaking its banks. These events, which occurred in 2010, 2016, and most recently in 2022, have affected several homes in the town. Many residents have had stormwater or floodwaters enter or nearly enter their premises during these storms, causing repeated concern and disruption for the community.
Alexandrina Council is currently working with the Ashbourne community to deliver a long-term solution to the ongoing flooding issues. Council is progressing complex planning and design stages to ensure the right infrastructure is delivered for the benefit of the community. To find out more about the project, visit our Ashbourne Stormwater Mitigation Project, dedicated page.

Chiton Rocks Toilet Upgrade
Work will start in late February to upgrade the public toilets behind the Chiton Rocks Surf Life Saving Club at Hindmarsh Esplanade, Hayborough.
This project is an action from our Public Toilet Management Plan 2024–2034 and is being funded in the 2025/26 Annual Community Plan. Weather permitting, the works are expected to be finished by June 2026.
The new toilets will comply with current disability access standards and building codes. The design includes accessible, gender-neutral and ambulant toilets, baby change facilities, and energy-efficient appliances. Sustainable building materials will be used.
The new toilet will have a shower wash-down area, a front veranda, a bench seat, solar power and battery systems, stainless fixtures, basins and troughs, feature lighting and hand dryers, security lighting and sensors, and honed concrete floors.
The existing 2016 mural by artist Barbary O'Brien at the Chiton Rocks facility will be retained and incorporated into the new design.
Landscaping with native plants will be established along with designated car parks.
Temporary portable toilets will be installed in the nearby area during construction.


Images: Left - current public toilet facilities near the Chiton Rocks Surf Life Saving Club. Right - artist's impression of new toilets.
There are no current projects listed in Clayton Bay.
Replacement of the Braeside Road Ford Crossing at Finniss
A project to replace the Braeside Road Ford Crossing at Finniss was completed in March 2026. The works included replacing the concrete crossing and culvert, minor upgrades to the crossing approaches, and replacing floodway and depth signage for the crossing.

Bristow Smith Avenue Stormwater
Minor works on the Bristow Smith Avenue, Goolwa, Stormwater Remediation Project are scheduled to start mid-March.
This project aims to improve existing stormwater infrastructure.
Works will include two new side-entry pits, a below-ground stormwater pipe, and a kerb adjacent to 44-54 Bristow Smith Avenue.
Images below: Area adjacent to 44-54 Bristow Smith Avenue and aerial map with red arrow pointing to site of works.

Billabong Road and Bunyip Street Stormwater Upgrade
This project is aimed at improving stormwater infrastructure to control water pooling after rainfall events. Works will include new below-ground pipe networks and kerbing. Design is currently being revised with onsite construction estimated for the second half of 2026.
Langhorne Creek Discovery Trail
A Wine Trail Project has been under consideration for a number of years by the community and industry representatives. Since late 2020, Alexandrina Council has been working closely with the Langhorne Creek Grape and Wine Association (LHCGWA) to progress a project to provide infrastructure, amenity and opportunities to enable visitors and locals to experience the uniqueness and the rich history of the Langhorne Creek wine region.
The intent of the Langhorne Creek Discovery Trail is to create a fit-for-purpose trail that provides interesting, accessible and safe ways to enable visitors and locals to visit wineries, attractions, and parks by both foot and on bikes.
The project contains two major elements:
- The delivery of physical infrastructure to support the hero element of the trail, a multi-use pathway providing a way for tourists to navigate a central 2.8km stretch safely and efficiently
- The development of an outstanding tourism product that encapsulates the cellar doors, experiences, environment and history of the Langhorne Creek region.
A business case was presented to the Council at the General Council Meeting in February 2024, where draft concept plans were also endorsed for public consultation.
Council has submitted an application to the Federal Government seeking full funding for a $7.1 million project to create a shared-use walking and cycling tourism trail through Langhorne Creek. The outcome of the submission to the Regional Precincts and Partnerships Program is expected in the fourth quarter of 2024.
Council also continues to collaborate with the Partnership Group on product packaging and destination marketing opportunities for the Langhorne Creek region.
Middleton Pedestrian Refuges
Following years of Council advocacy for safer pedestrian crossings in Middleton, the State Government, through the Department of Infrastructure and Transport (DIT) has funded three 'pedestrian refuge' crossings on Goolwa Road at Middleton.
Two of the pedestrian refuges were completed in early March 2024. A third refuge was built in February 2026.
Third pedestrian refuge constructed in February 2026
Under the National Road Safety Program, $200,000 was committed in March 2025 towards a third pedestrian refuge crossing on Goolwa Road, Middleton, near Thomas Street. This is a DIT project on a DIT road, with Council project managing the construction.
Media Release 2025 - State Government
Construction began on 12 February 2026. Final paving works were scheduled for March 2026.
Image: Indicative map of the location of three pedestrian refuge crossings in Middleton.
Public Toilet Upgrade
Work will start in late February to upgrade the public toilets behind the Middleton Arts and Crafts Building on Goolwa Road, Middleton.
This project is an action from our Public Toilet Management Plan 2024–2034 and is being funded in the 2025/26 Annual Community Plan. Weather permitting, the works are expected to be finished by June 2026.


Images: Left - current public toilet facilities behind the Middleton Arts and Crafts Building. Right - artist's impression of new toilets.
The new toilets will comply with current disability access standards and building codes. The design includes accessible, gender-neutral and ambulant toilets, baby change facilities, and energy-efficient appliances. Sustainable building materials will be used.
The Middleton toilet will have a feature brick wall, a front veranda, a bench seat, solar power and battery systems, stainless fixtures, basins and troughs, feature lighting and hand dryers, security lighting and sensors, and honed concrete floors.
Temporary portable toilets will be installed in the nearby area during construction.
Daranda Terrace Boardwalk, Milang
Soil testing investigations will take place around the Daranda Terrace Boardwalk on 16 September 2026 to support the design of a replacement boardwalk.
The existing timber boardwalk is nearing the end of its service life and is proposed to be replaced as part of a project currently planned for delivery in 2027–28.
Testing works are expected to cause minimal disruption. Further updates, including concept designs, will be shared with the community as the project progresses.
Milang Jetty
However, the end of the main Milang jetty was closed in late January due to damage from a berthing vessel. This has delayed the project and is likely to incur extra costs. The incident impacted the structural integrity of this part of the jetty and will require further engineering assessment, including an inspection by certified divers.
Council is reviewing the project to determine whether works on the other jetties can commence in the interim.
Milang Chapel, Stirling Street
Work has started on repairs, remediations and restoration to the historic Milang Chapel in Milang.
This church is one of the oldest European structures in Milang. It is listed as a Local Heritage Place and is currently used by the Milang & Districts Historical Society.
The chapel was built in 1866 and previously served as the Council Chambers for the District Council of Bremer, an RSL Hall and a local Scout Hall.
The work on this Council-owned building was funded in the 2025/26 Annual Community Plan. The project encompasses extensive structural and masonry repairs, underpinning, roofing and stormwater repairs, painting and perimeter paving.
All work is expected to be complete by the end of May 2026.

Image: The Milang Chapel is undergoing repairs that was scheduled to be completed by the end of May 2026.
Milang Soldiers Memorial Gardens - Rosemary Hedge Replacement
Council has undertaken works to manage the future care of the rosemary hedge surrounding the Soldiers Memorial at the Milang Soldiers Memorial Gardens.
Following consultation with key stakeholders involved with the Memorial Gardens, Council has removed two sections of the hedge that had reached their end of life and were showing signs of decline. Council has also removed rose bushes that had reached their end of life. The removed sections of the rosemary hedge and the removed rose bushes have been replaced.
Council looks forward to working with the community to ensure the Soldiers Memorial Gardens remain a meaningful and respectful space for Veterans, families, and the wider Milang community.

Road Works - Nangkita Road, Nangkita
Nangkita Road is designated as a Regionally Significant Freight and Community Access Route in the Southern and Hills Local Government Association 2030 Regional Transport Plan, ranking as the second most critical road in the plan. It is essential that the road remains safe and functional for all vehicles in all seasons.
Work commenced in May 2025 to upgrade an additional 2.91 km of Nangkita Road. The upgrade was completed in 2026.
Horseshoe Bay Beach Access Stairs
Horseshoe Bay beach access stairs close to the entrance to the Port Elliot Caravan Park are temporarily closed. This is due to the stair structure reaching the end of its useful life. The stairs were assessed as being beyond repair and have been removed for community safety reasons. Please note that beach access will be reviewed pending the outcomes of the Coastal Adaptation Plan for Horseshoe Bay.

Alternate beach access is available via the dune path, 60m to the right, or the stairs, 80m to the left.
Footpath works, Braemer Drive and North Terrace
Private contractors will commence footpath construction works on Braemar Drive and North Parade, Strathalbyn, from 1 December 2025. These works will include the installation of kerb and gutter, footpath construction, new property accesses, and road level corrections associated with an adjacent private development.
Work Zone Traffic Management and detours will be in place for the duration of the construction period, which is expected to take around three weeks. Please note these works are not Council-managed.
Stormwater works, South Terrace
Stormwater improvement works along South Terrace in Strathalbyn are almost complete. Minor defect repairs are scheduled for completion by 31 January 2026. Traffic management will be in place during these works to maintain a safe environment; however, both lanes of South Terrace will remain open, and access to adjacent businesses will be maintained at all times.
This project involved upgrading stormwater infrastructure along the southern side of South Terrace, near Murray Street, and at the intersection of East Terrace and Langhorne Creek Road. The scope of works included the installation of drainage systems, kerbing, and line marking.
For more information, please refer to the detailed map showing the location and extent of the stormwater works.
