The construction work to upgrade the highly used public toilets at Mount Compass commenced in April 2015 and was completed in August 2015. Work included:

  • Removal of existing roof sheeting and replacement with new galvanised corrugated roofing and translucent roof sheets
  • New render and paint finish to the interior and external walls
  • Re-exposure and restoration of the existing terrazzo toilet cubicle partitions
  • New wall tiles to the hand basin area, skirting tiles and feature wall tile throughout
  • New hand-basins and toilet suites and connection of the toilet cisterns to the wetlands water supply
  • New lighting and hand dryers
  • New timber slat screens to the ventilation openings
  • New decorative metal gates and new metalwork / artwork featuring local wildlife fixed to the exterior walls.

This work was undertaken by local building contractor Ian Saunders.

Toilet Block Inside Toilet Block