As part of the Strathalbyn Town Centre Streetscape Revitalisation project the Sunter Street bridge underwent restoration works for a period of five (5) weeks. Road works at the intersections of Sunter Street and Swale Street, and Swale Street and High Street, occurred concurrently under Section 33(1) of the Road Traffic Act 1961.

Sunter Street bridge was closed from October 2022 to December 2022. The intersections had partial closures during this time. Detour signs to guide road users around the works, all adjacent areas were accessible to local traffic. Electronic message boards were placed on the main approaches to Sunter Street giving prior notice of the closure.

Enquiries were directed to for works and traffic management to Outside Ideas . Council’s Project Design Coordinator was the lead on this project.